Risk Log Builder
Every project plan is a theory. A risk log is the honest accounting of where that theory might break — before the breaking costs money, reputation, or a missed launch window. This skill takes a plan or brief and returns a prioritized, owner-assigned risk register that a team can act on, not just file away.
It does not moralize or pad. It identifies real, specific risks, scores them on a consistent 1–5 × 1–5 grid using FMEA-style RPN (Risk Priority Number = Likelihood × Impact), writes a mitigation that reduces the score (not just a platitude), names a trigger for the contingency, and assigns an owner. Anything unconfirmed is marked [verify].
Skills this calls
brand-brain(required) — loads the active brand's constraints, voice, proof, and positioning. Risk language (especially customer-facing and legal risks) must obey the brand's banned words, proof standards, and regulatory context. Do NOT re-derive brand context here. Fallback if brand-brain is absent or returns no brand: do a thin direct read of the already-written brand file —~/.brandbrain/brands/.activethen that brand'sbrand.md; if nobrand.mdexists, ask the user for the brand name, its product category, primary compliance/regulatory exposure, and any known banned claims or proof constraints.pre-mortem-post-mortem-generator(optional, on request or when input is sparse) — run a pre-mortem pass to mine implicit assumptions; feed the output as risk seeds into Step 2 below. Call it before scoring if the user says "pre-mortem" or the brief has fewer than three explicit dependencies.deadline-drift-detector(optional) — when a project plan with dates is provided, call it to flag schedule-risk inputs (milestones already at risk or with zero float); import those directly into the Schedule bucket.go-no-go-gate-evaluator(optional) — on request, use it to map the completed risk register against launch-gate criteria (pass/fail per criterion). A well-mitigated risk log is direct input to a go/no-go gate.project-plan-generator-reviewer(optional) — when available, use its quality-gate output (missing owners, over-optimistic durations, no test time) as additional risk seeds in Step 2.
How a run works
Step 0 Load brand context ──► call brand-brain
Step 1 Classify mode ──► Quick Register (default) | Deep Register (on request)
Step 2 Mine risks ──► structured extraction across 6 buckets
Step 3 Score & rank ──► RPN = Likelihood (1–5) × Impact (1–5)
Step 4 Write mitigations ──► reduce the score, name a trigger, assign an owner
Step 5 Format + save ──► table (Quick) or full narrative (Deep); save to ./risks/
Step 0 — Load brand context (always first)
Invoke the brand-brain skill before any risk analysis. It returns the active brand's constraints — regulatory exposure, proof standards, banned claims, ICP fragility, and known operational gaps — that make certain risk categories higher-likelihood or higher-impact for this brand specifically. A generic risk log ignores these; this one doesn't.
Use the returned context to calibrate: a brand with [verify] claims in its proof vault carries higher reputation risk on launches; a brand in a regulated category (fintech, health) carries higher compliance risk; a scrappy brand with no dedicated ops owner carries higher execution risk.
Step 1 — Pick the mode
- Quick Register (default). A clean risk table: one row per risk, six columns (Risk, Bucket, Likelihood, Impact, RPN, Mitigation + Trigger, Owner). Ranked by RPN descending. Inline output; saved to
./risks/[project-slug]-risk-log.mdif the user names the project. - Deep Register (on request). Full narrative entry per risk: context paragraph, scoring rationale, mitigation task list (actionable, owner-assigned), contingency plan with explicit trigger condition, residual-risk score after mitigation. Plus an executive heat-map summary (3×3 visual grid: high/medium/low on each axis) and a top-3 risks one-pager for stakeholders. Triggers: "deep register," "full risk register," "narrative risk log," "board-ready," an explicit request for heat-map or executive summary.
Step 2 — Mine risks across 6 buckets
Work systematically through the plan or brief. Every risk needs a specific failure mode, not a category label. "Timeline slippage" is a category; "third-party API integration takes 3 weeks instead of 1 because vendor documentation is incomplete" is a risk.
| Bucket | What to probe |
|---|---|
| Execution | Dependencies, single points of failure, hand-offs, resource constraints, tool/vendor reliability |
| Schedule | Zero-float milestones, external deadlines, parallel workstreams competing for the same owner, approval cycles |
| Scope | Unanchored requirements, stakeholder expectation gaps, feature creep, missing acceptance criteria |
| Market / Audience | Audience assumption errors, seasonality, competitor response, demand validation gaps |
| Brand / Reputation | Unverified claims, off-brand messaging, regulatory exposure, negative press surface, social blowback triggers |
| Measurement | Tracking not set up before launch, undefined success metrics, attribution black holes, no baseline |
Pull from the input explicitly. If the input is thin, call pre-mortem-post-mortem-generator to surface implicit assumptions, then treat each failed assumption as a candidate risk.
Aim for 6–15 risks in Quick mode; more is not better — only include risks where a reader could do something. Duplicates, trivialities, and "risks" that are just features-not-yet-built belong in the scope log, not here.
Step 3 — Score with FMEA-style RPN
Score each risk on two 1–5 scales:
| Score | Likelihood | Impact |
|---|---|---|
| 1 | Remote (≤5% chance) | Negligible — no deadline, budget, or customer effect |
| 2 | Unlikely (5–20%) | Minor — recoverable with no external visibility |
| 3 | Possible (20–40%) | Moderate — delays launch or requires workaround customers notice |
| 4 | Likely (40–70%) | Significant — budget overrun, customer-facing degradation, or team morale hit |
| 5 | Near-certain (>70%) | Critical — kills the launch, regulatory breach, or major customer churn |
RPN = Likelihood × Impact. Range: 1–25. Rank descending. Risks with RPN ≥ 15 are Red (immediate mitigation required before launch); 8–14 Amber (mitigation plan in place, monitored weekly); ≤7 Green (accepted or low-cost mitigation sufficient).
Do not inflate scores to seem thorough. A project with five Green risks is a well-planned project, not a failure of imagination.
Step 4 — Write mitigations that actually reduce the score
Each mitigation entry has three parts:
- Mitigation action — what you do now or before the risk materializes. Specific, assigned, time-boxed. E.g., "Lock API spec with vendor in writing by [date]; add 3-day integration buffer to sprint 2."
- Contingency trigger — the specific observable signal that activates the contingency plan. E.g., "If vendor spec not confirmed by Day 5, escalate to PMO and activate backup library."
- Residual RPN — the expected RPN after the mitigation is in place. If you can't reduce it, say so and recommend escalation.
Owner is a role, not a person's name (e.g., "Campaign PM," "Paid Media Lead") — keeps the log useful when teams change.
Output format
Quick Register
## Risk Register — [Project / Campaign Name]
Brand: [slug, via brand-brain]
Generated: [date]
Input: [brief title or first line]
| # | Risk | Bucket | L | I | RPN | Status | Mitigation + Trigger | Owner |
|---|------|--------|---|---|-----|--------|----------------------|-------|
| 1 | [specific failure mode] | [Bucket] | 4 | 5 | 20 | 🔴 Red | [action] · Trigger: [signal] | [Role] |
...
### Top 3 (RPN ≥ 15)
[One sentence per risk: what it is, why it's rated this way, what the mitigation buys you.]
### Accepted risks (Green, no action required)
[Brief list — shows the reader the scope was considered, not ignored.]
Deep Register (on request, in addition to the table)
Per Red and Amber risk, add:
- Context: why this risk exists in this specific plan (one paragraph, no filler)
- Mitigation task list: 2–4 numbered actions with owner + due date
- Contingency plan: what happens if the trigger fires, who decides, in what timeframe
- Residual RPN after mitigation: and what risk remains accepted
Plus an executive heat-map (markdown 5×5 ASCII grid, L on x-axis, I on y-axis, risk numbers plotted) and a top-3 one-pager suitable for a stakeholder deck.
Persistence
Save the risk log to ./risks/[project-slug]-risk-log.md. Do not overwrite brand.md or any brand-brain companion file. On re-run (updated brief), diff against the existing log and surface new/changed/resolved risks — don't silently regenerate.
Principles (Non-Negotiable)
- Brand-brain first. No risk scoring before brand context loads — brand constraints directly calibrate likelihood and impact in the Brand/Reputation bucket.
- Specific failure modes only. Categories are not risks. Name the mechanism of failure.
- Mitigations must reduce the RPN. If a "mitigation" doesn't change the score, it's not a mitigation — it's an acknowledgment. Flag it as accepted risk or escalate.
- Honest scores. Don't inflate to look thorough or deflate to avoid alarm. Use the rubric, show the rationale.
- Owners are roles. Not names; roles survive team changes.
- Triggers are observable. A contingency with no trigger is decoration. "If X happens" must be a thing a human can see.
- Truth discipline. Any risk grounded in an unverified claim (regulatory exposure, market assumption, competitor behavior) is marked
[verify].
What Not to Do
- Don't pad to 20+ risks — more entries dilutes attention from the real ones.
- Don't use generic mitigation language ("monitor closely," "have a plan") — name the action, the owner, and the trigger.
- Don't re-implement brand context resolution; call
brand-brain. - Don't conflate a scope gap (missing feature) with a risk (failure mode of something that is planned).
- Don't score every risk as Red — calibrate honestly; a sea of Red means the rubric is broken, not the project.
- Don't save anything to the brand-brain data root;
./risks/only.
Quality Checklist (self-review before presenting)
brand-braincalled and brand context loaded; reputation/compliance risks calibrated against brand constraints?- Every risk is a specific failure mode, not a category label?
- RPN = L × I, scored against the defined rubric, with rationale?
- Every Red/Amber risk has a mitigation (action + trigger + residual RPN) and a role-based owner?
- Green risks listed as accepted (not silently omitted)?
- Quick: clean table ranked by RPN descending + top-3 summary? Deep: narrative + heat-map + one-pager?
- Saved to
./risks/[project-slug]-risk-log.md; no brand-brain files touched? [verify]on any score grounded in an unconfirmed assumption?